Design and implementation of build to sequence process.

(Duration 6 months)

Project lead for design and implementation of a sequence build programme for a new fully automated continuous moving flowline. Client required strong focus on integration between Supply Chain, Logistics, Quality and Operations to create robust material flow paths.

Factors considered

  • New Product range with highly configurable product

  • Significant investment on new production line showcasing lean principles

  • 600 orders per week single shift

  • Transactional and operation process to be designed and integrated

  • Multiple material flow paths required (PFEP) in line with inventory turn target

  • Integration with 2 satellite facilities supplying core components

  • Integration with a sister company supplying core component located in mainland UK

 

Key steps applied

  • Process mapped the extended order to delivery value stream

  • Risk analysis for potential failures completed

  • Designed control metrics to manage sequence adherence

  • Used system-based planning tools to set achievable sequence (SAP ERP)

  • Designed multiple material flow paths and assigned component families to each flow path (Extensive PFEP utilising Pull, Kanban etc)

  • Executed plans on time and drove sequence build for start-up utilising daily weekly and monthly governance

  • Weekly updated communication plans shared with impacted team

  • Laser focus on change management

 

Summary of results

  • Project delivered on time and on cost

  • Stabilised supply chain processes

  • Extensive PFEP designed and implemented

  • Engaged cross functional team driving sustained Sequence build adherence 95%+

  • Full change management plan in place with integration between all teams and sites

  • Continuous improvement structure implemented with suite of KPI’s for measurement

  • Increased throughput by 40% within the same footprint

  • Blue print and capability for all future sequence build initiatives

 